I know I’ve been quiet since I got things running around the one loop, so here’s a quick recap on where things sit right now.

Benchwork for Phase 3 is all built, up, and covered with foam (with the exception of the staging yard).

2016-03-23-11.04.44 2016-03-23-11.05.092016-03-23-17.01.41

An overall shot of the basement.

2016-03-23-17.02.20

Land forms have been taking shape on top of the base layer of foam too.

This is the future location of Wago Junction.

2016-04-09-18.31.06And the area where the railroad crosses the Codorus Creek on “Black Bridge” is also coming along.

2016-04-18-10.50.39

 

 

And, lastly, some progress on the bridge itself. It’s assembled from Micro Engineering girders, with an acrylic deck. Did you know Lowes sells sheets of Acrylic? I didn’t either, until the other day.2016-04-18-10.48.28 2016-04-18-10.50.43

 

One thought on “April 2016 Windsor St Progress Report

Comments are closed.